CIT Y 0 F M.A R Y S V ILL E
Marysville,Washington
RESOLUTION NO.C 9~
A Resolution of the City of Marysville approving
Street Department Construction Projects for 1978.
BE IT RESOLVED BY THE CITy COUNCIL OF THE CITY OF
MARYSVILLE,WASHINGTON AS FOLLOWS:
Section 1.The Street Department Construct~on
Projects for the year 1978,as described in Exhibit "A"
attached hereto,are hereby approved.
Section 2. The Street Department is hereby
authorized to proceed with the said Construction Projects
fifteen (IS)days ifter publicaton of this Resolution and
the attached exhibit.
PASSED by the City Coucil and APPROVED by'the Mayor
this --3']"II day of .J U be',1978.
THE CITy O~MARySVILLE'.\I'
BY~'~
M KY 0 R '.'I,.
~··f·...."\,."}
;.i '."f,~..,.("'.
,l,~",!....\.'~>,•\''I..~..I
BY'~liJetL,
APPROVED AS TO FORM:
·'
EXHIBIT "A"
LINNIHAN APARTHENTS
518 QUINN AVENUE
CURB AND GUTTER PAVING
PROJECT #T -041 -78A
Project consists of preparing and paving between new Curb and
Gutter and existing street and between curb and sidewalk.
PREPARATION:
251.26
70.35
22.10
64,,00
48.00
36.00
16.20
10,,00
2.00
519.91$
$-..-
---
40 manhours - - --- -
281.fringe benefits --
10 cubic yards @ $2.21 cu.yd.-
8 hours @ 8.00 per hour - - -
8 II @ 6.00 "II
8 II @ 4.50 " "
12 II @ 1.35 " "
2 "@ 5',,00 "II
1 "@ 2.00 II II -----,---:--:--
TOTAL -PREPARATION -
Labor - - - - - -
Labor - - - -
Crushed Rock --
Grader - - - - -
J.D.Loader - - -
66 Dump Truck
Pickups - - - - -
8 Ton Roller
12 Ton Trailer
PAVING:
Labor - - - -80 manhours - - - - - - - - -
Labor - - - - - -28%fringe benefits -,-- - - - -
Asphalt - - - - -100 tons @ $14.00 per ton - - -
Tack - - - - - -40 gals.@ .40 per gallon - -
73 Dump Truck - -10 hours @ 7.50 per hour -
66 Dump Truck - -12 II @ 4.50 II II _ _ _
Pickups - - - - -16 II @ 1.35"II _
Paving Box - - -10 "@ 3;00 II II _ - _
8 Ton Roller 8"@ 5.00 II "-- -
1 Ton Roller 8"@ 1.50"II - - -
Tack l-!achine - - 2 ,,@ .75 II II _ _ _
12 Ton Trailer _1 II @ 2.00 II II _
TOTAL -PAVING
$502;,52
·14°.71
1,400.00
16.00
75.00
54.00
21.60
30.00
40.00
12.00
1.,50
2.00
:I;2,295.33
TOTAL -JOB
DUPLEX
1619 -1621 -SIXTH STREET
CURB AND GUTTER PAVING
PROJECT #T -041 - 78B
Project consists of preparing and paving between new.Curb and
Gutter and existing street.
PREPARATION:
Labor - - - - - -
30 manhours - - - - - - - - - - -
$188.45
Labor - - - -
28~fringe benefits ...52.77-------
Crushed Rock 33 cubic yards]@-$2.21 cu.yd.-72.93
Grader ---4 hours @ $8;00 per hour 32.00
J.D.Loader - - -4 II @ 6.00 II 11 24.00
66 Dump Truck 4 II @ 4.50 II II 18.00
Pickups 6 II @ 1.35 II II 8.10--- - -
8 Ton Roller 1 II @ 5.00 II II 5.00
12 Ton Trailer -1 11 @ 2.00 II II --2.00
TOTAL -PREPARATION $403.25
PAVING:
Labor ---- - -
20 manhours - - - -
- ,----$125.64
Labor - --- - -
2810 fringe benefits --- - -
35.18
Asphalt - ----26 tons·@ $14.00 per ton 364.00
Tack - ---- -
6 gals.@ .40 pel'gal.2.40
73 Dump Truck - -4 hours @ 7.50 per hour - -
30.00
66 Dump Truck - -4 II @ 4.50 11 11 18.00
Pickups -----6 11 @ 1.35 II 11 8.10
Paving Box ---4 II @ 3.00 II 11 12.00
8 Ton Roller -..2 II @ 5.09 II II 10.00
1 Ton Roller --4 II @ 1.;50 II 11 6.00
Tack r-1achine 1 11 @ .75 II 11 .75
12 Ton Trailer -1 II @ 2.00 II II 2.00
TOTAL -PAVING -$614.07
TOTAL -JOB $1.017.32
..
CLIFF SANDS
1115 -FIFTH STREET
CURB AND GUTTER PAVING
PROJECT #T -041 -78C
Project consists of preparing and paving between new Curb
and
Gutter and existing street and between curb and sidewalk.
PREPARATION:
Labor - - - -
60 rnanhours -------- - --$376.16
Labor - - - -
28~fringe benefits - -
--- - -
105~32
Crushed Rock 33 cubic yards @ $2.21 cu.yd.-72.93
Grader ---14 hours @ $8.00 per hour 112.00
J.D.Loader -14 II @ 6.;00 II II 84.00
73 Dump Truck 4 II @ 7.50 II II 30.00
66 Dump Truck 14 II @ .4.;50 "II 63.00
Pickups ---10 II @ 1.35 II II 13050- -
8 Ton Roller 2 II @ 5.00 II II 10.00
TOTAL-PREPARATION $866.91
PAVING:
Labor - ---44 manhours - --- - - -
$285.03
Labor -- --28~fringe benefits - -
-- -
79.81
Asphalt -40 tons @ $14.00 pe;o ton - - -
560.00
Tack 20 gals.@ .40 per gallon 8;00
73 Dump Truck 6 hours @ 7.50 per hour 45.00
66 Dump Truck - -
8 II @ 4.;50 II II 36.00
Pickups -- ---12 II @ 1.35 "II 16.20
Paving Box -6 II @ 3.00 II II 18.00
8 Ton Roller 6 II @ 5.00 II II 30.00
1 Ton Roller 8 II @ 1.50 II II 12.00
Tack Uachine 2 II @ .75 II II 1.50
12 Ton Trailer -1 II @ 2.00 II II 2.00
TOTAL -PAVING $1,093.54
TOTAL -JOB $1,960.45
..
UNITED INSURAl'lCE AGENCIES,INC.
1803 GROVE STREET
CURB Al'lD GUTTER PAVING
l
PROJECT #T -041 -78D
Project consists o£preparing and paving between new Curb and
Gutter and existing street and between curb and sidewalk.
PREPARATION:
Labor - - -""--37 manhours - - -
------$231054
Labor -- -
.,.28~£ringe bene£its - - - ----64.83
Crushed Rock --18 cubic,yards @$2.21 cu.yd.-39.78
Grader -...-.--2 hours @ $8.00 per hour --16.00
J.D.Loader ""--10 II @ 6.00 II II 60.00
66 Dump Truck ""10 II @ .4.50 II II --45.00
Pickups -- -
4 II @ 1.35 II "5.40
8 Ton Roller 1 II @ 5.00 II "5.00--
TOTAL -PREPARATION -$467.55
PAVING:
Labor ----25 manhours -- -------$157.06
Labor ----28~£ringe benefits -- ---43.98
Asphalt - -- --18 tons'@ $14.00 per ton ---252.00
Tack -- - -
10 gals.@ .40 per gallon 4.00
73 Dump Truck 3 hours @ 7.50 per hour --22.50
66 Dump Truck 5 "@ 4.50 II "22050
Pickups - - -
6 "@ 1.35 11 11 8.10
Paving Box ---3 "@ 3.00 "11 9.00
8 Ton Roller 1 "@ 5.00 "II 5.00
1 Ton Roller - -
3 II @ 1050 "II 4050--
Tack Machine - -
1 11 @ .75 "11 .7~
12 Ton Trailer -1 "@ 2.00 " "
2.00
TOTAL -PAVING -:I>531.39
TOTAL -JOB -:I>998.94
..
WESTERGREEN SHEET METAL
-41l.th.AVENUE
CURB AND GUTTER PAVING
PROJECT #T -OU - 78E
Projec·t consists:of preparing and paving between new Curb and
Gutter and existing street and between curb and sidewalk.
PREPARATION:
Labor ...;...;- ---64 manhours ---------
Labor - - - -
28~fringe benefits -------
Crushed Rock -..;33 cubic yards @'$2.21 cu.yd...;
Grader ---12 hours @$8.00 per hour --
J .D.'Loader -12 II @ 6.00 II II
73 Dump Truck - -
12 II @ 7050 11 II --
66 Dump Truck 12 11 @ 4.50 II II
Pickups ---6 II @ 1;35 II II
8 Ton Roller 2 II @ 5.00 11 II
TOTAL -PREPARATION
$308.82
86.47
72.93
96.00
72;00
90.00
54.00
8.10
10.00
PAVING:
Labor ---..44 manhours - ---- ----$285.03
Labor --- -
28~fringe benefits -,-- --79.8l
Asphalt ---39 tons'@ $U~.OO per ton --546.00
Tack ----25 gals.@ .40 per gallon -10;00
73 Dump Truck ..-6 hours @ 7050 per hour - -
45.00
66 Dump Truck --8 II @ 4.50 II 11 36.00--
Pickups --- --10 II @ 1.35 II II 13.50
Paving Box ---5 11 @ 3.00 "II 15.00
8 Ton Roller --3 11 @ 5.00 II II 15.00--
1 Ton Roller 6 II @ 1.50 II II 9.00
Tack ~fachine --2 II @ .75 II II 1050
12 Ton Trailer 1 11 @ 2.00 11 11 2.00•
TOTAL -PAVING $1.°57.84
TOTAL -JOB $1.856.16
.1
•....'
..
FRED GROTIS
I'1INI HAREHOUSES -44th.AVENUE
CURB AND GUTTER PAVING
PROJECT #T -oU - 78F
Project consists of preparing and paving between new Curb and
Gutter and existing street and betwoen curb and sidewalk.
PREPARATION:
Labor - - - -
Labor - - - -
Crushed Rock
Grader - -...;
J.D.Loader -
73 Dump Truck ...;-
66 Dump Truck
Pickups - ---...;
8 Ton Roller
12 Ton Trailer
PAVING:
64 manhours - - - - - - - - -$
28~fringe benefits - - - - -
28 cubic yards @.$2.21 cu.yd.-
8 hours @ $8.00 per hour - -
8 II @ 6.00 II II
2 II @ 7.50 II II
8 II @ 4.50 II II
12 II @ 1.35 II II
2 II @ 5.00 II II
1 II @ 2.00 II II
TOTAL -PREPARATION -$
UO.67
114.99
61.88
64.00
48.00
15.00
36.00
16.20
10.00
2.00
778.74
Labor -- - -
34 manhour-s --- - --- -
---$222.22
Labor --28~fringe benefits -------62.22
Aspha.1t 28 tons .@ $14.00 per ton ,392.00--.-'-...
Tack --20 gals.@ .40 per gallon -8.00
73 Dump Truck - -4 hours @ 7.50 per hour - -
30.00
66 Dump Truck - -
6 II @ 4.50 II II -...27.00
Piokups - - -
8 II @ 1.35 II II 10.80--
Paving Box -6 ·11 @ 3.00 II II 18.00--
8 Ton Roller -..2 II @ 5.00 II II 10.00- -
1 Ton Roller --4 II @ 1.50 II II 6.00
Taok Maohine --1 II @ .75 II II .75
12 Ton Trailer -1 II @ 2.00 II II 2.00
TOTAL -PAVING $788.99
TOTAL -JOB -$1,567.73
•
•
,.
LIBERTY LANE
REBUILD WEST END
PROJECT #T -051 - 78
Project consists of rebuilding west end of Liberty Lane by
installing two catch basins,grading and reshaping approxi-
mately the last 120 feet and asphalting of same.Developer
to the west,Dujardin Custom Homes,Inc.gave the City $600.00
towards the cost of this and they also extended their storm
line to the end of their property.
PREPARATION:
Labor - - - - - -128 manhours - - - - - -
Labor - - - - - -28%fringe benefits --
Crushed Rock 55 cubic yards @ $2.21 cu.yd.-
CB 15 Bases - - -2 @ $78.83 - - - - - -
Frame &Grates - 2 @ 104.52-- - - - - - -
6 11 Plastic Pipe -100 feet @ $1;49 foot
4 11 Plastic Pipe -36 feet @ .32 foot - - - -
Grader - - - - -12 hours @ $8.00 per hour
J.D.Loader - - -20 II @ 6.00 II II.__
73 Dump Truck - -·.•4 II @ 7.50 II II
66 Dump Truck 16 II @ 4.50 II II
Pickups - - - - -32 II @ 1.35 II II
8 Ton Roller 4 II @ 5.00 II II
TOTAL -PRE~ARATION
PAVING:
$821.32
229.97
121.55
157.66
209.04
J49.00
11.52
96.00
120.00
30.00
72.00
43.20
20.00
$2,081.26
Labor ----20 manhours -- - -- - - - -
$125.64
Labor ..-- ---28%fringe benefits -------35.18
Asphalt ---40 tons·@ $14.00 per ton 560.00
Tack - ---5 gals.@ .40 per gallon -2.00
73 Dump Truck - -4 hours @ 7.50 per hour 30.00
66 Dump Truck - -4 II @ 4.50 II II 18.00
Pickups - - - - -
6 II @ 1.35 II II 8.10
Paving Box -- -
4 II @ 3.00 II II 12.00
8 Ton Roller --2 II @ 5.00 II II 10.00
1 Ton Roller --4 II @ 1.50 II II 6.00
12 Ton Trailer 1 II @ 2.00 II II 2.00
TOTAL -PAVING $808.92
.1
TOTAL -JOB $2,890.18