HomeMy WebLinkAboutR-0927 - Approving a Street Department Construction Project for 1979CIT Y 0 F MAR Y S V ILL E
Marysville,Washington
RESOLUTION NO.9"2.7
A Resolution of the City of Marysville approving
a Street Department Construction Project for 1979.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
MARYSVILLE,WASHINGTON AS FOLLOWS:
Section 1.The following Street Department Construction
Project for the year 1979 is hereby approved:
(a)Project No.T-041-79C:Preparing and paving
between new curb and gutter and existing street
adjacent to 1335 Cedar Avenue.
Total Cost:$3,920.90.
Section 2.The Street Department is hereby authorized to
proceed with said construction project fifteen (15)days after
publication of this Resolution.
PASSED by the City Council and APPROVED by the Mayor
this 2c:;'tl!-day of ..Ma w:.M ,1979.
THE CITY OF MARYSVILLE
ATTEST:
ByL1~L.d2
MAY 0 R
APPROVED AS TO FORM:
By~-=H.0e12e ee ~~City Attorney
~,.LINDBORG PLAT
1332 -1338 CEDAR AVENUE
CURB AND GUTTER PAVING
PROJECT #T - 041 -79C
Project consists of preparing and paving between new Curb and
Gutter and existing street.
PREPARATION:
Labor ---- -
- 150 manhours - - - - - - - - - - -$1,040.24
Labor-- - -30%fringe benefits -------312.07
Crushed Rock 72 cubic yards @ $2.435 cu.yd.-175.32
Grader - --20 hours @ $9.00 per hour 180.00
J.D.Loader - 20 "@ 6.00 ""120.00
73 Dump Truck 20 "@ 8.00 II II 160.00
66 Dump Truck 24 "@ 5.00 II II 120.00
54 Dump Truck 8 "@ 3.00 II II 24.00
Pickups - --30 "@ 1.50 II II 45.00
8 Ton Roller 2 "@ 5.50 II II 11.00
12 Ton Trailer 1 II @ 2.00 II II 2.00
TOTAL PREPARATION $2,189.63
PAVING:
Labor ----40 manhours - - - ---- --$277.40
Labor ----30%fringe benefits -------83.22
Asphalt - --75 tons @ $15.75 per ton 1,1$1.25
Tack ------20 gals.@ .42 per gallon -8.40
73 Dump Truck s hours @ $.00 per hour 64.00
66 Dump Truck $II @ 5.00 ""40.00
Pickups - --s II @ 1.50 ""12.00
Paving Box ---8 II @ 3.50 ""28.00
$Ton Roller 4 II @ 5.50 II II 22.00
I Ton Roller 6 II @ 2.00 "II 12.00
12 Ton Trailer 1 II @ 2.00 II II 2.00
Tack Ma chi.ne 1 "@ 1.00 II II 1.00
TOTAL PAVING $1,731.27
TOTAL JOB $3,920.90