RESOLUTION NO.9t.!
A Resolution of the City of Marysville approving
a Street Department Construction Project for 1980.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
MARYSVILLE,WASHINGTON AS FOLLOWS:
Section 1.The following Street Department Construction
Project for the year 1980 is hereby approved:
(a)Project No.T-056-80:Reconstructing and paving
of street in 500 block of Delta Avenue.Project
is approximately 54 feet wide by 300 feet long.
Total Cost:$6,427.15.
Section 2.The Street Department is hereby authorized
to proceed with said construction project fifteen (15)days after
publication of this Resolution.
ATTEST:
this
J~ASSED by the C7ty,Council and APPROVED by the Mayor9r_day of yYN/£,1980.
THE CITY OF MARYSVILLE
B,~I
II1AYOR
APPROVED AS TO FORM:
BY~~~C~Clerk
Bft.<&!JJ a ....,~
City Attorney
DELTA AVENUE RECONSTRUCTION
500 BLOCK DELTA AVENUE
PROJECT #T - 056 -80
Project consists of reconstructing and paving of street in 500
block of Delta Avenue.Project is approximately 54 feet wide by
300 feet long.Work will be done by Street Department Personnel
by the day labor method.
PREPARATION:
Labor - - - -120 manhours - - - - - -- ---- $905.10
Labor - - - -30%fringe benefits --- - -271.53
Crushed Rock -- 190 cubic yards @ $2.68 cu.yd.-509.20
Grader ---20 hours @ $9.00 per hour 180.00
J.D.Loader -18 "@ 6.00 " "
108.00
73 Dump Truck 12 "@ 11.25 ""13 5.00
66 Dump Truck 12 "@ 6.25 " "
75.00
Pickups - - -24 "@ 2.25 ""54.00
8 Ton Roller 3 "@ 5.00 ""15.00
Jack Hammer -2 "@ 2.00 ""4.00
TOTAL PREPARATION - $2,256.83
PAVING:
Labor - --- --100 manhours - - - --------$754.26
Labor -- --30%fringe benefits -------226.28
Asphalt - - -
200 tons @ $13 .27 per ton - -
2,654.00
Tack -- -- - -
20 gals.@ .514 per gallon -10.28
73 Dump Truck 20 hours @ 11.25 per hour 225.00
66 Dump Truck 20 "@ 6.25 ""125.00
Pickups - - -20 "@ 2.25 ""45.00PavingBox-20 "@ 3.50 ""70.00
8 Ton Roller 10 "@ 5.00 ""50.00
1 Ton Roller 4 "@ 2.00 ""8.00
Trailer - - -1 "@ 2.50 " "
2.50
TOTAL PAVING - $4,170.32
Materials - -
Labor - -
Equipment
$3,173.48
2,157.17
1,096.50
TOTAL JOB - $6,427.15
Total - $6,427.15