Loading...
HomeMy WebLinkAbout1767 - WA State Dept of Ecology - Agreement Amended - WQC-2018-MaryPW-00094 Grant for Stormwater Treatment Amendment 1AMENDMENT NO. 1 TO AGREEMENT NO. WQC-2018-MaryPW-00094 BETWEEN THE STATE OF WASHINGTON DEPARTMENT OF ECOLOGY AND City of Marysville PURPOSE: To amend the above-referenced agreement (AGREEMENT) between the state of Washington Department of Ecology (ECOLOGY) and City of Marysville (RECIPIENT) for the Downtown Stormwater Treatment Design and Construction (PROJECT). This amendment is needed to modify the short and Jong description and the scope of work, and to extend the expiration date of the agreement. The original project will now be divided into two phases. The amended agreement will include the design for both Phase I and Phase 2, and construction of Phase I only. ECOLOGY may amend the agreement at a future date to match the low responsive, responsible bid for construction of Phase I. Note: This amendment only includes the portions of the original agreement that have been changed in some way. Ifthere were no changes, it will not be referenced in the following portion of the amendment. IT IS MUTUALLY AGREED that the AGREEMENT is amended as follows: Expiration Date: Original: 06/30/2022 Amended: 06/30/2023 Project Short Description: Original: This project will improve water quality in the Snohomish River and the Ebey Slough through the installation of a lift station that will convey sto rmwater runoff to media filter systems at the site of the former Geddes Marina and Welco Lumber Mill, in the City of Marysville. The project will provide treatment for Total Suspended Solids (TSS), Oil (Total Petroleum Hydrocarbons), Dissolved Copper, Dissolved Zinc, and Total Phosphorus. Amended : This project will improve water quality in the Snohomish River and the Ebey Slough through the installation of a lift station that will convey stormwater runoff to media filter systems at the site of the former Geddes Marina, in the City of Marysville. The project will provide treatment for Total Suspended Solids (TSS), Oil (Total Petroleum Hydrocarbons), Dissolved Copper, Dissolved Zinc, and Total Phosphorus. Template Version I 0/30/2015 t)RIG,NAL State of Washington Department of Ecology City of Marysville Downtown Stonnwater Treatment Design and Construction Project Agreement No. WQC-20\8-MaryPW-00094 Project Long Description: Amended: Page 2 of6 This project will improve water quality in the Snohomish River and the Ebey Slough through the desi·gn of two treatment systems at the site of the former Geddes Marina, in the City of Marysville. The project site has a 140-acre contributing basin that is currently discharging untreated stormwater from the historic downtown area via a pipe system to the Snohomish River and the Ebey Slough. The RECIPIENT purchased the former Geddes Marina and Welco Lumber Mill sites for use as a park. In the park plan, space is allocated for stormwater treatment from the contributing basin. The Snohomish River and Ebey Slough are waterbodies with 303(d) listings for dissolved oxygen, temperature, bacteria, and pH. The Snohomish River tributaries also have a total maximum daily load (TMDL) plan for fecal coliform that requires business inspections, specific public education and outreach, pest waste stations, basin screening for illicit connections with sampling, and surface water sampling in streams. The RECIPIENT will design two independent stormwater treatment systems (Phase l and Phase 2), and install the Phase 1 treatment system including a lift station lhal will cu11vt:y !ilonnwater runoff to media filter systems. The systems will provide treatment for Total Suspended Solids (TSS), Oil (Total Petroleum Hydrocarbons), Dissolved Copper, Dissolved Zinc, and Total Phosphorus. Overall Goal: This project will help protect and restore water quality in Washington by reducing stormwater impacts from existing infrastructure and development. CHANGES TO THE BUDGET Funding Distribution .EG 180460 Funding Title: SFAP Funding Type: Grant Funding Effective Date: 04/01/2018 Funding Expiration Date: 06/30/2023 Funding Source: Title: Type: Funding Source %: Description: Title: Templa,tc Versiqn I 0/30/20 J 5 SFAP-SFY17 (WQC-2017) State 5% Funds come from the Model Toxic Control Account and State Building Construction Account. It funds projects that reduce the environmental impact of Stormwater pollution SFAP-SFY18 State of Washington Department of Ecology City of Marysville Downtown StonnwaterTreatment Design and Construction Project Agreement No, WQC-2018-MaryPW -00094 Type: Funding Source %: State 95% Description: Environmental Legacy Stewardship Account (ELSA) -State Approved Indirect Costs Rate: Recipient Match %: InKind Interlocal Allowed: InKind Other Allowed: Approved State Indirect: 0% 25% No No Is this Funding Distribution used to match a federal grant? No I SFAP Task Total Project Administration/Management $ 5,000.00 Design Plans and Specs, Environmental Review $ 901,666.67 Construction Management $ 240,000.00 Construction $ 5,520,000.00 Total: $ 6,666,666.67 CHANGES TO SCOPE OF WORK Task Number: 4 Task Cost: $5,520,000.00 Task Title: Construction Task Description: Page 3 of6 A. The RECIPIENT will, in accordance with ECOLOGY-accepted plans and specifications, complete construction of the project. The construction project will include installation of a lift station that will convey storm water runoff to media filter systems to mitigate runoff from approximately 35 acres of pollution generating impervious surfaces. B. Calculate and submit an equivalent new/re-development area for the completed retrofit project(s) using the methods outlined in Appendix M of the funding guidelines for State Fiscal Year 2018 Combined Water Quality Financial Assistance Program or other ECOLOGY-accepted method. Task Goal Statement: Construction of the project in accordance with ECOLOGY·accepted plans and specifications. Task Expected Outcome: Template Version I 0/30/2015 State of Washington Department of Ecology City of Marysville Downtown Stonnwater Treatment Design and Construction Project Agreement No. WQC-2018-MaryPW -00094 Constructed project will provide water quality benefits including reductions in Total Suspended Solids (TSS), Oil (Total Petroleum Hydrocarbons), Dissolved Copper, Dissolved Zinc, and Total Phosphorus. Recipient Task Coordinator: Jay Cooke Deliverables Number Description Due Date 4.1 Copy of the contract documents (e.g. bid announcement, bid award and bid tabulations). Upload to EAGL and notify ECOLOGY when upload is complete. 4.2 Copy of signed and dated construction contract. Upload to EAGL and notify ECOLOGY when upload is complete, 4.3 Construction progress reports and photos included in progress reports uploaui.:u Lu EAOL. 4.4 Completed equivalent new/redevelopment area determination. Upload to EAGL and notify ECOLOGY when upload is complete. Template Version I0/30/2015 Page 4 of6 State of Washington Department of Ecology City of Marysville Downtown StonnwaterTreatment Design and Construction Project Agreement No. WQC-2018-MaryPW -00094 Funding Distributfon Summnry Recipient I Ecology Share Funding Distribution Name Recipient Match % SFAP 25 % Total Template Version I 0/30/2015 Page5of6 Recipient Share Ecology Share Total $ 1,666,666.67 $ 5,000,000.00 $ 6,666,666,67 $ 1,666,666.67 $ 5,000,000.00 $ 6,666,666.67 State of Washington Department of Ecology City of Marysville Downtown Stormwater Treatment Design and Construction Project Agreement No, WQC-20 l 8-MaryPW-00094 AUTHORIZING SIGNATURES Page 6 of6 All other terms and conditions of the original Agreement including any Amendments remain in full force and effect, except as expressly provided by this Amendment. The signatories to this Amendment represent that they have the authority to execute this Amendment and bind their respective organizations to this Amendment. This amendment will be effective I 0/09/2020. IN WITNESS WHEREOF: the parties hereto, having read this Amendment in its entirety, including all attachments, do agree in each and every particular and have thus set their hands hereunto. Washington State Department of Ecology Vincent McGowan, P .E. Water Quality Program Manager Template Approved to Fonn by A ttnrney General's Office Template Version 10/30/2015 03/22/2021 Date City of Marysville By: 03/15/2021 Kari N Chennault Date Assistant Public Works Director Jon Nehring